A complex 2.2km on and off line road layout on the busy tourist route to the Wild Atlantic Way. Ground conditions changed from a 22m cut through boulder clay to a 6m excavation through peat and alluvium material. We deposited unsuitable peat to large peat dumps which required careful material management to prevent material loss onto public roads and adjacent properties. Quality - 0 NCR’s

Zero
Incidents / Loss time — H+S+W Performance
N59 Rossow Bends, Newport, Co Mayo
1
NCR’s
Quality
Lessons learned and Continual Improvement
15
Weeks final account
close out
2.2
Value million
euros
70
Weeks programme
completed on time