Data Centres
Cut/fill, pad excavation,concrete retaining walls, Substructure preparation, MV, HV, and LV ducting and Floor prep, internal drainage and coms, attenuation tanks and ponds. Quality - 1 NCR - lessons learned and Continual Improvement
Zero
Incidents / Loss time — H+S+W Performance
AWS DUB 57,58,06
1
NCR’s
Quality
Quality
Lessons learned and Continual Improvement
8
Weeks final account
close out
close out
5.5
Value million
euros
euros
52
Weeks programme
completed on time
completed on time